Project

Increased HV Supply Capacity to Factory

Location

Greencroft, County Durham

SERVICES PROVIDED
  • HV and LV design
  • ICP 20kV connection comprising:
  • GRP substation accommodation
  • 20kV metered ring main unit
  • 500kV transformer with close coupled
    LV board HV and LV cabling
  • Customer replacement LV switchboard
  • Construction to the adoptable
    standards of NPg
OVERVIEW

IUS delivered this work under our as an accredited Independent Connections Provider (ICP). Therefore, the works were carried out to the adoptable standards of the Distribution Network Operator, Northern Powergrid (NPg). The scope included the design, procurement, and installation of a 20kV distribution substation, low voltage sub-mains cabling, and a replacement customer low voltage switchboard to provide an increased supply capacity to the Tosoh Quartz factory in Greencroft, County Durham. The facility produces quartz glassware for the semiconductor industry for use in the processing of integrated circuits.

DESCRIPTION

IUS project managed the installation of the substation building to specification. The 115- meter feeder route encompassed 2 x 185mm aluminium 20kV XLPE Triplex cables to the point of connection onto the NPg network. Cable trenches were excavated on both private land and the public highway. IUS HV electrical fitters completed the installation of a 20kV
ABB safe plus ring main unit, 500kVA transformer with close coupled LV cabinet, earthing, protection, and metering cabling. IUS HV Jointers carried out the HV cable terminations. An IUS protection engineer conducted the pre-commissioning and witness testing for NPg. The IUS Senior Authorised Person provided the necessary safety documentation and oversight of the works. Customer LV sub mains cables were installed from the substation into the factory on high-level containment to supply a new low-voltage switchboard. Existing factory supplies were reconnected to the new switchboard during a planned outage giving the customer scope for their future expansion plans.

DOWNLOAD PDF VERSION

Careers in IUS

Read More

/sites/default/files/2023-09/careers_2_0.jpg

IUS News

IUS LRQA ISO 9001 & 14001
IUS renew LRQA ISO 9001 & 14001 certifications
Integrated Utility Services are proud to announce that we have successfully renewed our LRQA ISO 9001 (Quality Management) and ISO 14001 (Environmental Management) certifications, now valid through to 2028.
CONCOM Contractor Competency Audit
Integrated Utility Services successfully achieved a 100% score on our CONCOM Audit, established by The Humber Contractor Competency Forum, this plays a vital role in ensuring high standards across the contractor supply chain.
Integrated Utility Services Fleet
IUS Business Growth and Major Recruitment Drive for 2025
Integrated Utility Services (IUS) is pleased to announce continued growth in 2025, driven by a series of large-scale project wins and successful framework awards across the UK