Northern Powergrid Automation Installation

NPg Automation Installation

IUS secured a contract to deliver NPg Automation, which improves their customer service via network control remote switching capability ...

Client

Northern Powergrid (NPg)

Project

Urban Automation

Location

Hull

SERVICES PROVIDED
  • Civil excavation works
  • Remote Terminal Unit (RTU) installation
  • Testing and commissioning including with NPg control centre
OVERVIEW

IUS secured a contract to deliver NPg Automation, which improves their customer service via network control remote switching capability. This reduces electrical downtime for customers should a fault occur on the network. An RTU can be utilised to carry out remote High Voltage switching to quickly restore supplies. IUS are providing installation, commissioning, and technical support services to improve network restoration times via remote switching capabilities for 11kV ground-mounted switchgear. This is achieved via a central control centre over a secure radio network.

DESCRIPTION

The work involved carrying out a survey at the substation location to ascertain if the site is suitable for automation. The survey considered the existing 11kV switchgear installed on site; network design required by NPg and signal strength tests for connectivity onto the secure communication network. The survey identifies the automation equipment to be installed and if any civils work is required.

Civil works were completed on this site, which allowed cable connections to be installed to the existing switchgear and new RTU telecontrol equipment. The new RTU was installed on a frame with umbilical cables, connecting the new actuators, which are fitted to the 11kV switches. The design incorporates fault path indicators, which are automated and wired into the RTU. These indicate back to control if a fault occurs. A power supply for the RTU is connected to the Low Voltage feeder pillar within the substation compound, which is monitored by the RTU and control centre.

Commissioning of the site is carried out by the IUS Senior Authorised Person (SAP). Final connections were made on site, with all local operational tests carried out. Once satisfied that the installation was operationally ready the SAP contacted the control desk engineer and carried out any network reconfigurations required under a system outage, to allow remote operation. Remote testing was accomplished by the control desk engineer and the automation equipment was transferred into operational use on the NPg network.

DOWNLOAD PDF VERSION

Careers in IUS

Read More

/sites/default/files/2023-09/careers_2_0.jpg

IUS News

IUS Storm Darragh
Major Incident Response: Storm Darragh
As Storm Darragh swept across the region at the weekend with winds of up to 75mph, the IUS Overhead Line (OHL) Team was on the frontlines, stepping up to support Northern Powergrid in their response. 
Major Incident Response: Storm Bert
Integrated Utility Services Overhead Lines Teams supported Northern Powergrid with the response and restoration of overhead lines which were down due to Storm Bert this weekend.
Yorkshire Water Developer Day at University of Bradford Stadium