Loch Ness Regional – Raw Water Pumping Station (RWPS) - New Extra High Voltage (EHV) / Low Voltage (LV) Supply

Lochness Pumping Station

The development of a new RWPS on the west bank of Loch Ness formed part of Scottish Waters Regional Improvement Scheme ...

Client

Scottish Water

Project

Loch Ness Regional - Intake RWPS – Provision of new HV / LV supply

Location

Invermoriston, Loch Ness

SERVICES PROVIDED
  • Full design role
  • Principal contractor duties
  • Engagement with the SSEN, Forestry Scotland, client’s other contractors and all other key stakeholders
  • All civil works
  • Overhead line construction
  • SAP duties
  • Turnkey solution
  • Management consultancy of directional drilling
OVERVIEW

The development of a new RWPS on the west bank of Loch Ness formed part of Scottish Waters Regional Improvement Scheme. The scheme would provide an upgrade to improve the water quality and system resilience to the area. As part of the Scottish Water’s Supply Chain, IUS delivers contestable connections as an Independent Connections Provider. Therefore, IUS was appointed to design, procure and deliver the new electrical supply to operate this new pumping station.

DESCRIPTION

The works necessitated the installation of new H-Poles adjacent to the existing Scottish Power Energy Networks (SSEN) overhead line. These Hpoles would accommodate the installation of a 33,000/433V, 200kVA pole mounted transformer (PMT) and associated components. From the LV side of the PMT, a LV cable was laid to the new RWPS kiosk, terminating in a cutout beneath the installed current transformer metering panel. 

The feeder route necessitated a road crossing. To minimize disruption to traffic flow on the A82, the road crossing was undertaken by directional drilling.

Extensive engagement with SSEN was maintained throughout the duration of the works to ensure full compliance with their adoptable standards. On completion the substation was energised and the RWPS is now in full operation.

IUS undertook full design duties and operated as Principal Contractor (PC) for all our site works, liaising closely with Scottish Water’s own PC for the main development.

DOWNLOAD PDF VERSION

Careers in IUS

Read More

/sites/default/files/2023-09/careers_2_0.jpg

IUS News

blackburn meadows high voltage connections
Case Study: Blackburn Meadows WwTW upgrade for Yorkshire Water
This case study showcases Blackburn Meadows WwTW upgrade, and we are proud that Integrated Utility Services played a key role in helping deliver this major step forward for Yorkshire Water.
IUS Colleagues volunteer at Teesside Foodbank
Colleagues Volunteer at Teesside Foodbank
On 27th November, two of our colleagues, Kayleigh Forster and Daisy Ezard, volunteered at Tesco Billingham giving back to the community, supporting the Billingham & Stockton Borough Foodbank with the Trussell Trust. 
Road Safety Week 2025 at IUS
IUS Supports Road Safety Week 2025
Integrated Utility Services is proud to support our group-wide commitment to Road Safety Week, reminding everyone that safe vehicles save lives.