Leeds City Station Sandford Street Switchgear Replacement

Leeds City Station

Network Rail awarded IUS the contract for the replacement of the existing 11kV distribution substation at Leeds City Station ...

Client

Network Rail

Project

Leeds City Station

Location

Leeds

SERVICES PROVIDED
  • Relocation of existing cleaners compound with a purpose built cladded structure
  • Construction of substation buildings for Network Rail and Northern Powergrid
  • Installation of domestic electrical supplies within buildings
  • Installation of fire alarms
  • Installation of 11kV switchgear
  • All 11kV electrical protection
  • Installation of containment
  • Installation of 11kV cables
  • Jointing and termination works
  • All civil activity
  • Removal of redundant switchgear
OVERVIEW

Network Rail awarded IUS the contract for the replacement of the existing 11kV distribution substation at Leeds City Station. The existing oil filled switchgear was replaced with new apparatus. The works were coordinated to incorporate changes to the Northern Powergrid equipment.

DESCRIPTION

Owing to existing 11kV switchgear at Leeds City Station reaching the end of its life span, a solution was required for the seamless renewal of the switchgear, whilst maintaining supplies to an operational train station. The former location of the existing 11kV substation was below ground in an area known as the ‘Dark Arches’. The train station was built on a set of vaulted arches with an area occupying distribution substations.

Logistically the location of this existing substation was unsuitable, therefore a purpose built substation was constructed at platform level, containing both Northern Powergrid and Network Rail equipment in separate sides of the building.

Two parallel 11kV feeders were taken directly from Northern Powergrid’s Whitehall Road primary substation. The approximate route length was 0.25 miles. Two parallel circuits then fed the Network Rail FKI Eclipse switchgear.

Each of the six Network Rail 11kV circuits supplied six 11,000/433V ground mounted transformers. These transformers were resupplied via new 11kV cabling. IUS managed all the critical power outages to deliver the works whilst trains continued to operate.

DOWNLOAD PDF VERSION

Careers in IUS

Read More

/sites/default/files/2023-09/careers_2_0.jpg

IUS News

IUS LRQA ISO 9001 & 14001
IUS renew LRQA ISO 9001 & 14001 certifications
Integrated Utility Services are proud to announce that we have successfully renewed our LRQA ISO 9001 (Quality Management) and ISO 14001 (Environmental Management) certifications, now valid through to 2028.
CONCOM Contractor Competency Audit
Integrated Utility Services successfully achieved a 100% score on our CONCOM Audit, established by The Humber Contractor Competency Forum, this plays a vital role in ensuring high standards across the contractor supply chain.
Integrated Utility Services Fleet
IUS Business Growth and Major Recruitment Drive for 2025
Integrated Utility Services (IUS) is pleased to announce continued growth in 2025, driven by a series of large-scale project wins and successful framework awards across the UK