Gorbals Pumping Station 11kV Contestable Connections & Private Infrastructure Works

Gorbals Pumping Station

IUS completed the electrical construction works associated with the prestigious Gorbals Pumping Station project. The power for the three 1.2MW pumps ...

Client

Scottish Water / Amey Black and Veatch

Project

Gorbals Pumping Station

Location

Corselet Road, Darnley, Glasgow, Scotland

SERVICES PROVIDED
  • Outline and detailed design (Electrical and Civil)
  • System studies (P28/P29/G5-4)
  • 11kV contestable connection work
  • On site private 11kV infrastructure work
  • Procurement of equipment
  • Installation of 11kV switchgear
  • Installation of step down transformers
  • Installation of 11kV cables
  • Installation of control/metering cables
  • Heavy lifting operations
  • Protection design
  • Testing and commissioning
  • Preparation of handback documentation
OVERVIEW

IUS completed the electrical construction works associated with the prestigious Gorbals Pumping Station project. The power for the three 1.2MW pumps required a 3.6MVA connection to the existing Scottish Power Energy Networks 11kV network. IUS were appointed to undertake the design and installation of the adoptable 11kV contestable elements of the connection works along with the clients own 11kV infrastructure within the Pumping Station itself.

DESCRIPTION

The project involved the provision of a bespoke GRP enclosure to house the Distribution Network Operator (DNO) 5 panel 11kV switchboard, with the clients 11kV switchgear located within the fabric of the main Pump House, constructed by others. Two independent 3.6MVA circuits were provided from individual primary substations on the DNO 11kV network.One feeder for normal service conditions and one circuit for security of supply in the event of a fault on the principal supply.

Both 11kV cable routes to the Pumping Station involved extensive excavation over circa 7km, including under three railway bridges and over numerous road bridges. This required additional engineering solutions to negotiate. The IUS scope of works included interface with all stakeholders, most notably Network Rail, local councils, the DNO, SEPA, as well asScottish Water. The private electrical infrastructure installed by IUS included an eight panel 11kV switchboard, three 2MVA transformers, one 0.8MVA transformer, 11kV cabling, control/metering wiring, electrical protection and substation ancillary equipment.

DOWNLOAD PDF VERSION

Careers in IUS

Read More

/sites/default/files/2023-09/careers_2_0.jpg

IUS News

IUS Storm Darragh
Major Incident Response: Storm Darragh
As Storm Darragh swept across the region at the weekend with winds of up to 75mph, the IUS Overhead Line (OHL) Team was on the frontlines, stepping up to support Northern Powergrid in their response. 
Major Incident Response: Storm Bert
Integrated Utility Services Overhead Lines Teams supported Northern Powergrid with the response and restoration of overhead lines which were down due to Storm Bert this weekend.
Yorkshire Water Developer Day at University of Bradford Stadium