Persimmon Homes Multi Utility Install: Laneside Farm Phase 1

Persimmon Homes engaged IUS to deliver Multi Utility installations for a 450-plot housing development in Morley, Leeds, including gas, water, and electrical connections, as well as the construction of two HV substations.

Generator Connection In Lieu Of Substation Connection For New Homes Development Toot Lane - Boston - Lincolnshire

The scope of these works was to provide the Developer with a temporary supply as the Distribution ...

Lovell Homes - Howden - Goole

The scope of works included the design, procurement and installation of UDE (Unit Distribution Equipment) substation ...

Careers in IUS

Read More

/sites/default/files/2023-09/careers_2_0.jpg

IUS News

From Contestable Connection to Long-Term Asset Management
This project showcases the breadth of capability within Integrated Utility Services (IUS), supporting our customer, Taylormade Timber from the initial contestable connection through to private 11kV infrastructure works and long-term asset management via an Operation & Maintenance agreement.
IUS respond to storm Boelo
IUS responds to Storm Boelo
Over the last two days, our Integrated Utility Services Overhead Lines teams have been out across the North East and Yorkshire supporting Northern Powergrid's response to Storm Boelo.
Teesside Solar Farm Substation
IUS Install Infrastructure for Teesside Solar Farm
IUS supported High View Energy and ROC Energy with the delivery of the new electrical connection for the ongoing project at Teesside Solar Farm. The substation has been constructed in advance of the solar panels being installed.