Substation Installation & Contestable Connection at Montagu Hospital

The project was undertaken on behalf of Doncaster and Bassetlaw NHS Foundation Trust, and the work took place at Montagu Hospital, which is located in Mexborough.

The scheme encompassed the installation of two substations with a HV connection off site and LV connections to existing panels on site. IUS installed one substation to the adoptable standards of Northern Powergrid, as well as a customer owned substation. Both substation buildings were single-story brick and block construction, with service voids underneath to support cable routing.

Castle Hill Hospital

IUS were contracted by Hull University Teaching Hospitals NHS Trust to install the 11kV Infrastructure for a new 5MWe Solar Farm on land adjacent to Castle Hill Hospital ...

Freeman Hospital

Robertson CE Ltd has constructed a new building at the Freeman Hospital site, now named the Day Treatment Centre. IUS's scope of works included the design ...

Careers in IUS

Read More

/sites/default/files/2023-09/careers_2_0.jpg

IUS News

Tioxide Transformer Installation
Tioxide Restart Production at their Greatham facility
We were proud to support the site last year with the replacement of a 4MVA, 11kV/3.3kV transformer, helping to ensure the electrical infrastructure was ready to support future operations.
Substation Woodhouse Lane Leeds
Major Infrastructure Upgrade at Leeds City Council's Woodhouse Lane Car Park
Integrated Utility Services (IUS) is proud to have successfully delivered a major infrastructure upgrade at Leeds City Council's Woodhouse Lane car park.
Supporting the future growth of East Midlands Airport
We have been contracted to deliver a transformer replacement project at East Midlands Airport, increasing electrical capacity while strengthening resilience across critical airport operations.