Emergency Response & Repair following 11kV Fault on a Contracted Customer Network

New Switchgear

Client

N/A

Project

Emergency Response & Repair following 11kV Fault on a Contracted Customer Network

Location

Spalding, Lincolnshire

New Switchgear
New Switchgear
SERVICES PROVIDED
  • Out of hours response to a call following loss of supply
  • Project and fault management
  • Generator connection to restore temporary supplies
  • Safe systems of work
  • Switchgear removal
  • New switchgear installation
  • 11kV cable jointing and terminations
  • Testing and commissioning
  • Restoration of permanent supply
  • Handback documentation
OVERVIEW

Integrated Utility Services (IUS) carried out works at a large food manufacturing facility that provides products for supermarkets throughout the UK. Their intake substation is operated via National Grid Electricity Distribution (NGED). The HV configuration included an aged, oil filled (Brush) combined 11kV Switchboard, with 3 NGED owned panels and 3 customer owned panels.

There was also a separate, customer owned two panel Schnieder Electric CE2/CE6 switchboard, connected via a HV cable loop. Their power supply is essential and the benefit of having an Operation & Maintenance Agreement with IUS, for their private 11kV network, was demonstrated following a fault.

We have had historic problems with the old Brush switchgear with various fault repairs completed on this network. However, it was a flashover on the NGED owned 11kV metering Circuit Breaker, which caused a loss of supply and an emergency response from both IUS and NGED.

DESCRIPTION

The IUS Senior Authorised Person was called out to a loss of supply at the facility, attended the site and assisted NGED following a Distribution Network Operator Circuit Breaker trip. 
 

To initially restore supplies, generation was arranged by the customer with IUS implementing the required safe system of work including HV switching and the issue of safety documents. This arrangement would provide a temporary supply solution and enable NGED to carry out any required repair works on their own equipment. 
 

Following consultation with the client, it was decided the most appropriate way to proceed would be to replace the Brush oil filled switchgear with new Schneider Electric SF6 insulated apparatus. This would be achieved by extending the existing Schneider Electric switchboard with a further 3 panels. With safety documentation in place, the old Brush switchgear was disconnected and removed. 

The new Schneider Electric apparatus was installed and 11kV cable jointing and terminations where undertaken.  Working collaboratively with the customer and NGED the installation was completed, tested, commissioned and energised. This would allow normal supplies to be restored, and the generators to be disconnected.

DOWNLOAD PDF VERSION

Careers in IUS

Read More

/sites/default/files/2023-09/careers_2_0.jpg

IUS News

IUS are Carbon Neutral
IUS sponsor Wates Group Charity Dinner
IUS sponsor Wates Group Annual Charity Dinner 2024 in aid of Suicide Prevention
Bee Sustainable UK Initiative