ESB engaged Integrated Utility Services (IUS) to install new units to replace a number of their existing Ecar charging points. The work was undertaken at various locations throughout Ireland. IUS was selected for our civil capability, as well as familiarity with the installation of ducting for ESB networks. IUS complied with all ESB standards and procedures, resulting in a growing network of public charging points.

Client

ESB Networks

Project

ECARS New Installation and Replacement Programme

Location

Across Ireland

ECARS EV Charing Points in Ireland
ECARS EV Charing Points in Ireland
SERVICES PROVIDED
  • Charger and interface installation
  • Ducting and Cabling
  • Civil Engineering
  • Signage, Bollard and Plinth installation
  • Roadmaking’s
  • Drainage works
  • Full reinstatement of works including concrete and macadam areas
  • Traffic management
  • Project management
  • PSCS Health & Safety management
  • Customer and public interface
OVERVIEW

ESB engaged Integrated Utility Services (IUS) to install new units to replace a number of their existing Ecar charging points. The work was undertaken at various locations throughout Ireland. IUS was selected for our civil capability, as well as familiarity with the installation of ducting for ESB networks. IUS complied with all ESB standards and procedures, resulting in a growing network of public charging points.

DESCRIPTION

The project involved installing new and replacing existing Ecar charger points in over 100 locations throughout Ireland.


The work sites included built up areas, shopping centre carparks and remote rural locations. IUS managed the projects, complying with Health and Safety Regulations, traffic management procedures and local council requirements. All works were completed to ESB Specifications and Standards.


The scope of services included siting the new Ecar units on plinths cast in concrete, excavation of cable ducts, cabling between the Ecar charger points, installation of interface unit and the ESB mini pillar, signage, road markings, full reinstatement, and completion of test certification prior to sign off by our client, ESB.

DOWNLOAD PDF VERSION

Careers in IUS

Read More

/sites/default/files/2023-09/careers_2_0.jpg

IUS News

Tioxide Transformer Installation
Tioxide Restart Production at their Greatham facility
We were proud to support the site last year with the replacement of a 4MVA, 11kV/3.3kV transformer, helping to ensure the electrical infrastructure was ready to support future operations.
Substation Woodhouse Lane Leeds
Major Infrastructure Upgrade at Leeds City Council's Woodhouse Lane Car Park
Integrated Utility Services (IUS) is proud to have successfully delivered a major infrastructure upgrade at Leeds City Council's Woodhouse Lane car park.
Supporting the future growth of East Midlands Airport
We have been contracted to deliver a transformer replacement project at East Midlands Airport, increasing electrical capacity while strengthening resilience across critical airport operations.