Persimmon Homes Multi Utility Install: Laneside Farm Phase 1

Persimmons Case Study

Persimmon Homes engaged IUS to deliver Multi Utility installations for a 450-plot housing development in Morley, Leeds, including gas, water, and electrical connections, as well as the construction of two HV substations.

Client

Persimmon Homes West Yorkshire

Project

Multi Utility Install: Laneside Farm Phase 1

Location

Laneside Farm, Morley, Leeds

Persimmon Homes Utilities Case Study
Persimmon Homes Utilities Case Study
SERVICES PROVIDED
  • Install – Electric
    • Install & Connect 2x High Voltage Substations
    • 6000 Meters of High Voltage (HV) & Low Voltage (LV) Electric Cable
  • Install – Water
    • 3000 Meters of Water Pipe
  • Install – Gas
    • 1260 Meters of Gas Pipe
OVERVIEW

Persimmon Homes engaged IUS to deliver Multi Utility installations for a 450-plot housing development in Morley, Leeds, including gas, water, and electrical connections, as well as the construction of two HV substations.

DESCRIPTION

Integrated Utility Services (IUS) is delivering a flagship Multi Utility project for Persimmon Homes West Yorkshire, playing a key role in site design and infrastructure development.

We have connected one HV substation in collaboration with NPg (DNO) and Murphys (IDNO), with a second substation set to go live in February 2025. Working closely with Yorkshire Water, we are installing the water network for future adoption.

Design approval and legal consents were secured in early 2023, allowing installation of gas, water, and electrical infrastructure to industry standards, including NSP001 (NPg) and Murphys’ Technical Guidelines. Full on-site work began in April 2023, with in excess of 30 visits from our Multi Utility team over phase 1. We installed two LV connections for temporary supplies, ahead of substation commissioning.

In phase 1, we have completed one HV substation, with the second scheduled for commissioning in February 2025, installed one-third of the mains, and connected 90 plots. Our work has undergone multiple audits, earning Grade 1 Health and Safety ratings from Lloyds. Persimmon Homes remains a valued client, and we look forward to continuing our strong partnership.


“ IUS and Persimmon Homes (West Yorkshire) have a long standing relationship and have worked closely together on a number of schemes across our region. The team at IUS are very helpful and proactive when it comes to delivering new services to the development. They navigate challenges posed by the ever changing industry and specific site constraints and are a pleasure to work alongside.”

Sam Sowrey - Technical and Commercial Director, Persimmon Homes (West Yorkshire)

DOWNLOAD PDF VERSION

Careers in IUS

Read More

/sites/default/files/2023-09/careers_2_0.jpg

IUS News

Gigafactory in Sunderland
Project Spotlight: AESC UK gigafactory battery factory in Sunderland
Integrated Utility Services (IUS) is proud to partner with Wates Group on the AESC UK gigafactory battery factory in Sunderland! 
Persimmon Homes Multi Utility Install: Laneside Farm Phase 1
Persimmon Homes engaged IUS to deliver Multi Utility installations for a 450-plot housing development in Morley, Leeds, including gas, water, and electrical connections, as well as the construction of two HV substations.